Project cost of Bullet train estimated as Rs. 1,08,000 Cr
As per Joint Feasibility Study report of 2015, the project cost of Mumbai-Ahmadabad High Speed Rail (MAHSR) Corridor was estimated as Rs. 1,08,000 Crore and completion period was indicated as 8 years. The timeline is also dependent on availability of land and site. This information was given by the
As per Joint Feasibility Study report of 2015, the project cost of Mumbai-Ahmadabad High Speed Rail (MAHSR) Corridor was estimated as Rs. 1,08,000 Crore and completion period was indicated as 8 years. The timeline is also dependent on availability of land and site. This information was given by the Minister of Railways Ashwini Vaishnaw in a written reply to a question in Rajya Sabha. He informed that out of total land requirement of approx. 1389.5 ha. about 1381.9 ha. land has been acquired. All the civil contracts of the project have been awarded. The delay in land acquisition especially in the State of Maharashtra has impacted the project adversely.